Brij Cement Logo
Brij Cement Expert's Choice Logo
Technical Support+977-9801091143
Cement Calculator Dealer Locator
  • Products
  • Knowledge Hub
    • For Home Builder
      • Home Maintenance
      • Interior Designing
      • Vastu
    • For Engineers & Architects
      • Architectural marvels
      • Innovative Techniques
      • Technical Programmes
    • For Contractors
      • Best Practices
      • Building Solutions
      • Masons’ Programmes
    • For Large Projects
      • Programmes
      • Projects
  • Building Tools
    • Cement Calculator
    • EMI Calculator
    • Dealer Locator
    • Vastu
  • Careers
Brij Cement Logo Expert's Choice Logo
  • Products
  • Knowledge Hub
    • For Home Builder
      • Home Maintenance
      • Interior Designing
      • Vastu
    • For Engineers & Architects
      • Architectural marvels
      • Innovative Techniques
      • Technical Programmes
    • For Contractors
      • Best Practices
      • Building Solutions
      • Masons’ Programmes
    • For Large Projects
      • Programmes
      • Projects
  • Building Tools
    • Cement Calculator
    • EMI Calculator
    • Dealer Locator
    • Vastu
  • Careers
Building Design and Construction Program

Building Design and Construction Program


Programs describe the sequence in which tasks must be carried out so that a project (or part of a project) can be completed on time.

Programs will often identify:

  • Dates and durations allocated to tasks.
  • A critical path (the sequence of critical tasks upon which the overall duration of the programme is dependent).
  • Tasks which can only be carried out after other tasks have been completed.
  • Tasks which can be carried out simultaneously.
  • 'Float' within tasks that are not on the critical path (that is, delays that can be incurred without affecting the critical path). Identifying float can be helpful in highlighting where it may be possible to transfer resources to tasks that are on the critical path.
  • The need for specific resources such as plant, services or materials and their lead time.

Preparing a program should not be a paper exercise that simply records what has already happened or what is likely to happen. For a program to be effective, it must be used as a tool to help plan activities, monitor progress and identify where additional resources may be required.

Programs can be prepared for a number of different purposes:

  • The client's overall program, which may include more than one project, activities leading up to the appointment of consultants, works outside the scope of the main contract (such as the supply of equipment), migration strategy, and an ongoing program for operation and evaluation once the development is complete.
  • Project program: 'The overall period for the briefing, design, construction and post-completion activities of a project.'
  • A design program scheduling tasks from the appointment of the consultant team to the appointment of the contractor. This might be a simple gantt chart incorporating each consultants planned resources for each stage which is then monitored and reported to the client.
  • Information release schedules, setting out when the consultant team should issue production information to the contractor in order for the works to progress and when information produced by the contractor (or their sub-contractors) should be issued to the consultant team for comment and integration into the overall design.
  • The contractor's master program, scheduling construction activities.
  • Approvals programs.
  • Tender or procurement programs.
  • Manufacturing programs.
  • Delivery programs.
  • Installation programs.
  • Testing and commissioning programs.
  • Short-term look ahead programs.

On large projects, the client may appoint a program consultant to prepare a detailed program for the project (including an outline program for construction). Once the contractor is appointed, they will take responsibility for programming the works.

When preparing a program, particular attention should be given to:

  • Long-lead items.
  • Pre-contract works (such as demolition or site clearance).
  • Prefabricated elements.
  • Works outside of main contract (such as work by statutory undertakers).
  • Relationships with other projects.
  • Phasing and sectional completion.
  • Decision points (gateways). Decision points often appear as milestones on programs, with no consideration given to whether the individuals required to make the decision will be available, or how long it might take to make that decision. Wherever possible key client decisions should be programmed to take place at existing meetings, with briefing material issued in advance, enabling the client to make informed decisions.

The contractor's master program is not part of the contract documents, and is not enforceable under all forms of contract. The completion date (and perhaps stage or sectional completion dates) are enforceable and failure of the contractor to meet the completion date may lead to a claim by the client for liquidated damages.

Contracts will generally require that the contractor progresses the works regularly and diligently and failure of the contractor to meet the dates on the master program might be evidence that this is not the case.

A design program defining deliverables might be incorporated into consultant's agreements, however, this is difficult to enforce (due in part to activities of third parties outside the consultant’s control such as planning authorities, client or stakeholder actions, consultation processes, etc.), and generally, the only recourse the client has is to threaten termination for non-performance in the event of consistent programme failure.

Kedia Organisation Logo
  • House No. 301, Ward No. 1 Lalupate Marg, Hattisar
  • P.O. Box 13368, Kathmandu Nepal
  • +977-01-5970708 / +977-01-5970771
  • info@kediaorganisation.com
  • www.kediaorganisation.com

Important Links

  • About Us
  • Image Gallery
  • Video Gallery
  • News & Articles
  • CSR/Event/Sponsors
  • Client’s Testimonial
  • Careers
  • Contact
  • Technical Support

Latest News & Articles

Brij Cement collaborated with CESS-Nepal as a trophy sponsor in the 13th Civil Engineering Exhibition Cum Competition

Brij Cement collaborated with CESS-Nepal as a trophy sponsor in the 13th Civil Engineering Exhibition Cum Competition

February 8, 2023
Technical Consultation at Pokhara Metropolitan City

Technical Consultation at Pokhara Metropolitan City

August 11, 2022
Awareness Program

Awareness Program

July 11, 2022
Copyright © Brij Cement. All rights reserved.
Designed & Developed by Proxy Infotech Solutions Pvt. Ltd.

Upload Your Resume

Submit your application, we will get you back soon!